Amur Gas Chemical Complex says construction 19.5% finished - News Archive - PRIME Business News Agency - All News Politics Economy Business Wire Financial Wire Oil Gas Chemical Industry Power Industry Metals Mining Pulp Paper Agro Commodities Transport Automobile Construction Real Estate Telecommunications Engineering Hi-Tech Consumer Goods Retail Calendar Our Features Interviews Opinions Press Releases

Amur Gas Chemical Complex says construction 19.5% finished

MOSCOW, Jun 30 (PRIME) -- Construction of a U.S. $10–11 billion Amur Gas Chemical Complex of Russian petrochemical holding Sibur and China’s Sinopec is 19.5% finished, it said on Wednesday in a statement published on its telegram channel.

“The progress of the Amur Gas Chemical Complex project amounts to 19.5%. At the construction site, 155 units of equipment and 1,096 personnel are working,” the statement read.

The production capacity of Amur Gas Chemical Complex will amount to 2.3 million tonnes of polyethylene and 400,000 tonnes of polypropylene per year. The launch was scheduled for the end of 2024.

End %%md/jst%%

30.06.2021 17:16
 
 
Share |
To report an error select text and press Ctrl+Enter
 
 
Central Bank Official Rate
1W 1M 1Y
USD
EUR 98.6447 +0.6177 03 may
USD 92.0538 +0.2747 03 may
Stock Market Indices
1D 1W 1M 1Y
MICEX
micex 3477.42 +0.22 18:50 02 may
Stock Quotes in RUR
1D 1W 1M 1Y
GAZP
gazp 163.22 0.00 23:50 02 may
lkoh 8085.50 0.00 23:50 02 may
rosn 582.00 0.00 23:50 02 may
sber 307.10 -0.37 19:04 02 may
MICEX Ruble Trading
1D 1W 1M 1Y
USDTD
EURTD 98.4850 +0.6900 15:00 02 may
USDTD 92.1050 +0.5500 17:44 02 may